Week Start
Task
October 4
Annotate existing film posters/DVD covers
October 11
Audience Research e.g. Questionnaire
October 18
Summary of audience research
October 25
Produce a production schedule
November 1
Produce first draft storyboard (organise props and actors)
November 8
Rough draft of DVD cover and poster
November 15
Second draft of DVD cover and Poster
November 22
Final storyboard, first video shoot with review, cast and location photo shoot and final draft of DVD cover and poster.
November 29
Second video shoot with review footage.
December 6
Video editing, arrange clips on timeline.
December 13
Final Video Editing



































This is our first Production Schedule. We created this to make sure that we were keeping in time with our deadline. We also wanted to make sure that we added enough detail into our trailer and planning. So far we have tried to keep up to date with our schedule and make sure that our blog posts have the most information as possible, however it has been quite hard to keep up with our schedule as we have found other activities we needed to do that were more important. We have had to rearrange some of the tasks in our schedule for example, we are doing our first filming and editing in the week of December 6th.

We are also intending to our rough draft of our DVD cover and poster this week.